Overview: May 2020 Sprint #589
Comments
New website progress
New docs include the following:
Hoping to deploy the new website over the coming weekend. We're down to about 18 issues and 3 PRs. When we started, I think it was 30 issues and 9 PRs. |
The new re-frame website is now up at: http://day8.github.io/re-frame/ The re-frame logo has been tweaked. See it here: And a release candidate for 1.0.0 is also out Also, we're now down to about 16 issues and 2 PRs. Now we begin on the meatier issues. |
The task of addressing meatier issues is now slightly delayed.
We are down to 13 open issues and 2 PRs, which is a numerical measure of some success. |
Many improvements to the docs have been made recently. Too many to mention but some are notable:
Also:
Numerically, we're at 13 issues and 3 pull requests. |
Isaac and I are doing a three-week-long sprint on re-frame - starting 4th May. Isaac's time is being paid for by ClojuristTogether funding. My time is paid for by Day8. So between us, we have about 6 man-weeks.
At a high level, the strategy is:
This will likely take longer than six man-weeks. And then there will be necessary adjustments to re-frame-10x. To quote a line from the movie
Get Shorty
"This is only the second day, and we're already two weeks behind." But, one step at a time, let's just see how we go.I will update this issue with new thoughts as we go. We will probably engage with the community via the clojurians
#re-frame
channel. If you are interested in the process, please keep an eye out there.The text was updated successfully, but these errors were encountered: